Posting Date: 09/Sep/2020
Anjung Kecil oil field development The Anjung Kecil oil field development includes Anjung Kecil well-head platform and Marginal Marine Production Unit (MaMPU)-1 floating production storage and offloading (FPSO) vessel.
Vestigo procured a low pressure-condensate recovery system (LP-CRS) unit for the field in September 2016. The company performed a geophysical survey at the oil field using research and seismic support vessel Java Insignia in March 2019. The Anjung Kecil well-head drilling operation commenced using tender-assisted drilling rig Mist in June 2019. The rig reached the oil field from Singapore’s Keppel Feels Pier. The vessels involved in the drilling work were 246ft-long Mist, 70m-long Grade One Manjung 8, and 75.27m-long Ena Samurai. A 1.26km-long dynamic subsea power cable will be laid between the FPSO and the well-head platform as part of the field modification plan.